Logo for SK Enterprises

S K Enterprises' Synapsis System Help Section

 

Project Manager


  1. Starting a project.
  2. Creating tasks.
  3. Assigning resources.
  4. Entering and tracking costs.
  5. Examining the project.
  6. Tracking the progress of the project.
  7. Generating reports.
  8. Some project management basics.



VI. Tracking the progress of the project.

The "Tracking" tab is where we begin to examine how to track a project's progress. Basically, tracking is an on-going input of actual project results. First, click on the "Tracking" tab.

Tracking Initial Screen

Note that the "Tracking" tab (highlighted in white) has four sub-tabs: "Task," "Cost," "Resource," and "Report." The default sub-tab is the "Task" sub-tab, which we see displays each task, the "Task Start," the "Task End," and "Duration." You will recognize the initial display as the projected values, which we entered ealier. The values in this "Task" sub-tab will eventually be 'actual' data that you enter as the project progresses, but the intial display is taken from the projections. There are two selection columns, "Update Actuals" and "Modify" task. The "Update Actuals" checkbox allows you to record the actual task duration, start and end dates. The "Modify Task" checkbox will update task projections using the information you input on this screen. If you click the "Modify Task" checkbox, Project Manager will re-calculate the start date, end date, and or duration based upon the values you entered, as well as make any "Pre-" task adjustments only for the selected task. For example, suppose we changed the start date and duration for task G. Project Manager would adjust the end date and make sure the new start date did not violate any "Pre-" task conditions for task G (task G cannot start until at least 1 hour after task F finishes). Thus, at this point in the evolution of Project Manager, you,as project manager, would still have to re-check all other task schedules and "Pre-" task conditions.

Whether or not you choose to use the "Task" sub-tab to update your projections, the main use for the "Task" sub-tab is to track actuals (task events that actually happen and when they actually happen).  This way, you can create and maintain a record of how your projections compared to what actually happened.

The next sub-tab is the "Cost" sub-tab.

Cost Tracking Initial Screen

The "Cost" sub-tab also has two views, one for tasks and one for resources. The task view shows each task along with projected cost information next to input text boxes for recording actual cost information (fixed, total, and to-date). The resource view shows the same information for resources. While this ability to record, display and compare actual costs with projected costs is useful, it can be cumbersome to record costs in this manner because you would have to pre-calculate all of the costs before they could be entered. In order to make it easy to enter cost information, Project Manager provides the "Resource" sub-tab.

Resource Tracking Initial Screen

The "Resource" sub-tab lists each resource with its task assignments, projected regular assignment hours, and projected overtime assignment hours. It also provides input text boxes where you can enter incremental actual hours worked since the last update and a box to enter the date the hours are valid through (which defaults to the current date). This allows you, or others, to regularly enter hours worked by each resource on each task. When you enter the hours in the "Resource" sub-tab, that information is used to calculate costs and populate the "Cost" sub-tab costs.

Resource Tracking Entering Data

Here we have recorded some hours for Ann and Bill. To enter the information, just click the "OK" button.

Resource Tracking Data Entered

We note that the information has been recored and the "Date Updates" column now shows the date that the hours were updated. But what about the "Cost" sub-tab?

Cost Tracking after Resource Tracking

We see that the "Actual To-Date" columns now have data values recorded and displayed for the tasks and resources we recorded in the "Resource" sub-tab. If we navigate back to the "Cost" tab, we see that the "Actual Cost" column is now populated with the costs calculated from the hours we previously inputted.

Cost Screen with Actual Data

You can now, if you wish, navigate back to the "Cost" sub-tab of the "Tracking" tab and input any actual fixed costs incurred, and, or update the total costs.  A note with regard to the allocation of fixed costs between resources and tasks: Project Manager leaves this allocation to you, so you must insure that if a resource has a fixed cost, you allocate that fixed cost among the tasks to which you assign that resource.

As you have seen, Project Manager provides simple yet powerful means to track project costs from projected to actual among both tasks and resources. We next turn our attention to generating reports using Project Manager.

VII. Generating reports. (top)

Currently Project Manager provides 15 distinct reports grouped into four categories. You generate reports by navigating to the "Report" sub-tab of the "Tracking" tab.

Reporting Initial Screen

The four report categories are Summary, Cost, Task, and Resource. You may select to generate up to four reports at once, one from each category. To choose a report, simply click the desired category checkbox and click the report radio button and then click the "OK" button. You will notice that Project Manager does not generate a ready-to-print, formatted report. Instead Project Manager generates a text report using a comma separated value (CSV) format. Future enhancements are planned that will provie the option of generating pre-formatted reports, but the CSV formats provide an extra degree of flexibility - along with some additional work.

Report Screen - Report Display

Here we have selected two reports: the "Project Report" from the Summary category, and the "Time Report" from the Cost category. But, you might ask, "What do we do with these?" First, open a text editor, or word processing program. Second, within the text box of one of the reports, select the entire report text.

Reporting Selected Report Text

Third, copy the text to the clipboard (usually <CTRL>-c). Fourth, paste the text into the text editor or word processor you opened in step 1.

Reporting Text Editor

We run Linux, so we'll use K-Edit, but it works the same using Microsoft's Notepad. Fifth, just save the file and give it the file extension CSV (e.g., "cost_report_1.csv"). Sixth, open your spreadsheet program (Excel, Gnumeric, Calc, etc.). Seventh, open the ".csv" file you just saved, or import the file, whichever your spreadsheet program requires.

Reporting Import to Spreadsheet

We are using OpenOffice.org Calc and are importing the file "cost_report_1.csv" as a comma-delimited file, which is being parsed as shown. Finally, you can save the newly created spreadsheet and then format your report however you wish. You can then print it, or send it out via e-mail. "Eight steps!" you say. Actually, those eight steps probably take under a minute to accomplish - go ahead, try it.

Let's take a closer look at each of the reports. The first report is the "Summary - Project" report.

Summary Project Report

This report is a summary of several project dimensions: start and end dates, work hours, costs, task status(total, in-progress, late, finished), and resource status (person, material, overtime, and total). This is a basic summary report that tends to compare projected and actual task and resource data. The next report is the "Summary - Task" report.

Summary Task Report

The "Summary - Task" report displays each task, its projected duration, start and end dates, percent complete together with actual costs and hours of resources assigned. The next report is the "Summary - Work" report.

Summary Work Report

This report shows the standard work calendar along with any non-standard work calendars for resources. The next category is the "cost" category, which contains three separate reports: "Time," "Budget vs. Actual," and "Budget Analysis." The last "Summary" report is the "Summary - Critical" report, which generates a critical path/task analsysis.

Summary Critical Report

The "Critical Task Analysis" is fairly important in project management because it identifies tasks that must start and finish on schedule, otherwise the project itself will fall behind schedule. The "Summary-Critical" report shows, for each task, the early and late start and finish times (on a scale relative to time=0),  the slack or float (how much time a task can slip without impacting the project finish date), and whether or not the task is a critical task.

There are three "Cost" category reports. The "Cost - Time" report shows weekly task cash flow over the life of the project using task projections.

Cost Time Report

The next report, the "Cost - Budget vs. Actual" report, shows a task-by-task comparison of projected versus actual costs for total and to-date.

Cost Budget vs. Actual Report

Finally, we examine the "Cost - Budget Analysis" report, which is, in most respects, a report version of the display from the "Cost" tab.

Cost Budget Analysis Report

The next report catehory is the "Task" category, which consists of four reports: "Pending," "In-Progress," "Completed," and "Late."

Task Completed Report

All of the "Task" reports have the same format, but show different tasks depending on whether the task is pending, in-progress, completed, or late, based upon the current date relative to the projected dates. The report shown above is the "Task - Completed" report. You can see that these "Task" reports show each task, resources assigned to the task, task hours and resource assigned hours.  The report also provides task and resource assignment start and end dates as well as "Pre-" task relationships.

The final category of reports is the "Resource" category. The first report is the "Resource - List" report.

Resource List Report

This report lists each resource, the total hours they've been assigned on the project, each task to which they've been assigned including the assigned hours, start date and end date. The next report is the "Resource - Time," or "Resource - Schedule" report.

Resource Schedule Report

This report shows resource assigned hours for each week of the project by resource and task. The next report is the "Resource - Periodic" report, which displays each resource, followed by each week of the project and the tasks to which the resource is assigned for that week along with the assignment hours, start date-time, and end date-time.

Resource Periodic Report

The final report is the "Resource - Overtime" report, which shows, by resource for each resource with scheduled, or projected, overtime hours by task and date.

Resource Overtime Report

These are the current set of reports available in Project Manager. Future plans include additional reports, formatted reports, and a custom reporting capability.

Well, we've now completed our examination of Synapsis Project Manager.  We hope you have found these pages helpful and that you find your use of Project Manager to be rewarding.

(top)